Construction of the China–Kyrgyzstan–Uzbekistan Railway: Project Status and Implementation Details
The implementation of the China–Kyrgyzstan–Uzbekistan railway project is ahead of schedule. The total cost of the main line is estimated at 4.7 billion dollars.

The China–Kyrgyzstan–Uzbekistan railway construction project, which officially launched on December 27, 2024, in Jalal-Abad, aims to develop the transport infrastructure of Central Asia. The 532.53 km long main line will follow the Kashgar — Torugart — Makmal — Jalal-Abad — Andijan route, with 312 km of the track running through the territory of Kyrgyzstan.
Kyrgyzstan's Minister of Foreign Affairs Jeenbek Kulubaev described the project as an important element in forming a unified transport system for Eurasia. According to him, the new road will expand the region's logistics capabilities and serve as an indicator of the high level of trust between the participating countries.
According to the intergovernmental agreement, the preliminary cost of the project is 4.7 billion dollars. Financing is carried out through a joint project company, where China's share is 51%, and Kyrgyzstan and Uzbekistan hold 24.5% each. China is providing a loan of approximately 2.3 billion dollars for a term of 35 years, while the remainder of the funds is contributed by the participants to the authorized capital in proportion to their shares.
Construction work is proceeding ahead of schedule. As reported in August 2026 by Uzbekistan's Minister of Transport Ilkhom Makhkamov, completion of the construction is possible at least a year earlier than planned. At that time, about 17% of the total volume of work had been completed.
Currently, the construction of eight large bridges is underway at the site. More than 10,000 workers and over 7,000 units of special equipment are involved in the large-scale construction.